Timeline
810 McDonald
Street
Regina, Saskatchewan
February |
Stucco banner work completed Concrete floor poured in CRU3 Interior steel stud installed CRU3 Rough in plumbing completed CRU2 and 3 Roof membrane install completed HVAC main distribution complete both CRU2 and 3 |
|
January |
Exterior stucco work continues. Exterior store front glass installed. Preparation for concrete floor. |
|
December |
Roof membrane commences. Roof top HVAC installed. Stucco work continues and the CRU1 portion is complete. Interior work on CRU2. |
|
November |
Exterior block walls completed Roof deck installed Rework of existing space commences |
|
October |
Construction of exterior block walls New building banner preparation and insulation Grade beam work completed and preparing for block wall construction Metal canopy removed Piles for addition completed and grade beam work commences Installation of new T5 light fixtures in existing tenant space |
|
2011 |
Building redevelopment to multi-tenant commercial space with 3 units |
|
2006 |
||
1979 |
New 22,720 square foot building built for Fort Ignition Limited |